This major site overhaul involved importing more than 28,000 tons of crushed concrete. All of this material was generated in-house at our recycling locations. This project also involved exporting large quantities of unsuitable clay materials & importing structural/sandy fill. To accommodate the operational needs of Veransa, this project worked in 3 phases.